London, 28 November 2024 - Energean plc (LSE: ENOG, TASE: אנאג) is pleased to provide the following update on recent operations and the Group's trading performance in the nine-months to 30 September 2024. The numbers contained herein are unaudited and may be subject to further review and amendment.

Mathios Rigas, Chief Executive Officer of Energean, commented:

"We are pleased to announce another strong quarter, marked by a 61% year-on-year increase in adjusted EBIDTAX from our continuing operations[1]. Our production in Israel remains unaffected by geopolitical events, recording a 39% year-on-year increase, and we welcome the announcement of the ceasefire in Lebanon.

"Our operations continue to deliver energy security to Israel and the broader region through the optimisation of production from our FPSO, which has been operating at 99% uptime[2], underscoring our operational resilience. Progress on key development projects have also been robust: the Katlan area in Israel remains on schedule and the second oil train has been installed on the FPSO. Upon commissioning, the second oil train will increase the liquids production capacity, supporting enhanced operational performance.

"The targeted sale of our Egypt, Italy and Croatia portfolio (the "Transaction") to an entity controlled by Carlyle International Energy Partners ("Carlyle") is on track for completion by or just after year-end 2024, supporting our focus on core assets, deleveraging, and delivering incremental shareholder returns.

"Additionally, our Prinos carbon storage project in Greece, now recognised as an EU Project of Common Interest, has secured material funding from the Greek Recovery and Resilience Facility ("RRF").

"Energean is committed to delivering on its strategic priorities: operational excellence, maximising shareholder value, and broader sustainability objectives. A key pillar of our strategy is ensuring a reliable dividend, supported by our focus on securing long-term cash flows that are independent of commodity price fluctuations. We are also pleased to declare today another quarterly dividend, bringing the total distributed to shareholders since the announcement of our policy in 2022 to $541 million."

Operational Highlights

  • Group production for the period was 156 kboed (83% gas), a 31% increase year-on-year (nine-months 2023: 119 kboed). Production from the continuing operations1 for the period was 117 kboed (85% gas), a 40% increase year-on-year (nine-months 2023: 84 kboed).

o In Israel, FPSO uptime2 (excluding planned shutdowns) was 99% for the nine-months to 30 September 2024. Q3 production averaged 135 kboed.

o Day-to-day production remains unimpacted by the ongoing geopolitical developments.

  • Post-period end in October, the second oil train (Israel) lift was safely and successfully performed.

o Post-lift, installation and commissioning activities are expected to take up to 6-months to complete, which will result in an increase in liquids production capacity.

  • Katlan (Israel) development progressing on schedule, with first gas expected in H1 2027 as previously announced.

o Energean is planning the drilling campaign for 2026, which will include the Athena and Zeus development wells plus options for further exploration and appraisal.

  • Prinos carbon storage project (Greece) Front-End Engineering Design activities progressing:

o NSAI CPR confirmed an annual storage capacity of up to 3 million tonnes and a total project-life capacity of 66 million tonnes (2C contingent) of CO2.

o In October, the European Commission approved, under EU state aid rules, the EUR 150 million grant from the Greek RRF to support the maturation and development of the first phase of the project, allowing the transition of Prinos into a new decarbonisation hub.

o In addition EnEarth, the 100% owned subsidiary of Energean focused on carbon storage, has applied for funding under the Connecting Europe Facility.

  • 20% reduction in Tors and Wenlock (UK) total decommissioning expenditure expected following the takeover by Energean as operator and signing of the Petrodec UK Limited ("Petrodec") contract[3]; UK production has outperformed expectations year-to-date.
  • Group Scope 1 and 2 emissions intensity of 9.0 kgCO2e/boe, a 7.1% reduction (nine-months 2023: 9.7 kgCO2e/boe). Scope 1 and 2 emissions intensity for the continuing operations1 was 7.2 kgCO2e/boe.

Financial and Strategic Highlights

  • Revenues for the period were $1,363 million, a 35% increase (nine-months 2023: $1,016 million), of which $1,033 million is associated with the continuing operations1.
  • Adjusted EBITDAX for the period was $894 million, a 44% increase (nine-months 2023: $623 million), of which $706 million is associated with the continuing operations1.
  • Group leverage[4] (net debt/annualised adjusted EBITDAX) maintained at 2.5x versus 30 June 2024 (2.5x) and lowered versus 31 December 2023 (3x).

o Group cash as of 30 September 2024 was $284 million, including restricted amounts of $5 million, and total liquidity was $443 million[5]. This includes cash for the continuing operations1 of $272 million, including restricted amounts of $5 million, and total liquidity of $431 million5.

  • Strategic sale of the Egypt, Italy and Croatia portfolio to an entity controlled by Carlyle targeted to complete by or just after year-end 2024, subject to customary regulatory and antitrust approvals, which are currently underway with a number having already been obtained.

o UK carve out from the Transaction perimeter has been successfully completed.

o Energean expects to have sufficient proceeds to redeem the $450 million PLC Corporate Bond or to fund growth opportunities or a combination of both, in accordance with the terms of its financing documents.

o Energean also continues to expect to have sufficient funds to facilitate a special dividend of up to $200 million.

  • Energean intends to refinance its 2026 Energean Israel Limited bond and is evaluating a range of options to maintain an efficient capital structure, freeing up liquidity for its Katlan development and growth strategy.
  • Q3 2024 dividend of 30 US$ cents/share declared today, scheduled to be paid on 30 December 2024[6].

o Including the Q3 2024 dividend, approximately $541 million will have been returned to shareholders since payments began, over half of the Group's target to return $1 billion to shareholders by the end of 2025.

o The Group expects to redefine its dividend policy upon Transaction closing, consistent with its core objectives of capital discipline and maximising returns to shareholders.

Outlook

  • 2024 Group production guidance updated to 150-155 kboed (from 155-165 kboed), of which 110-115 kboed is associated with the continuing operations1. This reduction is due to Israel, which reflects lower than expected sales in November owing to weather conditions and market dynamics and, for the lower end, an assumption of flat month-on-month sales for December.
  • 2024 Group exploration reduced to $95-120 million (from $115-150) million, of which $60-75 million is associated with the continuing operations1, reflecting actual spend associated with the recent drilling operations in Morocco.
  • 2025 guidance will be provided in January 2025 when Energean issues its next Trading Statement & Operational Update.

Production

Nine-months to 30 September 2024 KboedNine-months to 30 September 2023 Kboed% changeTen-months to 31 October 2024 Kboed
Israel1158339%112*
Europe2.01.625%1.9
Total continuing operations 111784 [7]40%114
Disposal Group393415%39
Total Group production156119 731%153

*October figure reflects the scheduled FPSO shutdown for the second oil train lift.

Financials

30 Sept '24 Energean Group30 Sept '23 Energean GroupIncrease/ (Decrease) %30 Sept '24 continuing operations 130 Sept '23 continuing operations 1Increase/ (Decrease) %
Sales revenue ($m)1,3631,01635%1,03368251%
Cash cost of production per barrel (including royalties; $/boe)1011(9)%910(10)%
Cash G&A ($m)27264%151225%
Adjusted EBITDAX ($m)89462344%70643961%
Development and production expenditure ($m)47742313%24820720%
Exploration expenditure ($m)8525254%6121191%
Decommissioning expenditure ($m)253380%112450%
30 September 2024 Energean Group30 June 2024 Energean Group
Net debt ($m) (including restricted cash)2,9652,902
Leverage 4 (net debt / adjusted EBITDAX)2.5x2.5x
Full Year 2024 guidance*
GroupContinuing operations 1
Total production (kboed)150 - 155 (from 155 - 165)110 - 115 (from 115 - 125)
Consolidated net debt ($ million)2,900 - 3,000-
Cash Cost of Production (operating costs plus royalties; $ million)550 - 600375 - 405
Development & production capital expenditure ($ million)600 - 700320 - 380
Exploration expenditure ($ million)95 - 120 (from 115 - 150)60 - 75 (from 80 - 105)
Decommissioning expenditure ($ million)40 - 5015 - 20

*Unchanged unless otherwise noted.

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note