Updated EMH DFS at Cinovec Project

In brief · summary, not quotable

European Metals Holdings Limited has updated its Definitive Feasibility Study (DFS) for the Cinovec Lithium Project, confirming it as a long-life producer of battery-grade lithium carbonate strategically positioned to supply the European electric vehicle and energy-storage sectors. The updated DFS, which now covers a 23-year production schedule due to ASX requirements, reports a pre-tax Net Present Value (NPV) of US$1.455 billion and an Internal Rate of Return (IRR) of 14.8%, with C1 costs at US$12,621 per tonne and All-in Sustaining Costs at US$13,879 per tonne. Initial capital expenditure is estimated at US$1.72 billion net of approved grants, which include up to EUR 360 million from the Czech Government and US$36 million from the EU Just Transition Fund. The company is actively pursuing project financing and finalising off-take agreements with major European battery and automotive groups.

Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your EMH notes

EMH UPDATED DFS CONFIRMS LONG-LIFE BATTERY-GRADE LITHIUM CARBONATE PRODUCER AT CINOVEC STRATEGICALLY POSITIONED TO SUPPLY EUROPEAN EV AND ENERGY-STORAGE SECTORS

Further to the announcement by the Company on 19 December 2025, and following discussions with the ASX, the DFS has been updated for the following reasons.

  • The ASX will not permit the inclusion of the final 4 years of the production schedule thereby reducing the production schedule from 27 years to 23 years. The Company has been forced to accept this refusal despite its confidence that the production schedule as originally year disclosed in its AIM announcement of 19 December 2025 is in compliance with the JORC Code.
  • This reduction in the mine plan has resulted in a reduction in the Pre-tax NPV8 of the Cinovec Project from 1.712bn to 1.455bn and the Pre-tax IRR from 15.3% to 14.8%.
  • The Company is highly confident that the inferred resources in years 24-27 of the Original mine plan will be converted to indicated resources upon additional infill drilling of the inferred resources (all prior upgrades from inferred have converted 100% of the inferred resources to indicated resources) however in order to allow trading in its shares on the ASX to continue it has reduced the mine plan for the DFS to 23 Years.
  • The Company is working with its consultants to revise the mine plan to revert to 27 years in a manner which is compliant with JORC and also with the ASX's interpretation thereof and to issue an updated DFS with these additional years included in the near future.

The updated DFS announcement is disclosed below.

HIGHLIGHTS

  • Definitive Feasibility Study (DFS) confirms Cinovec as a long-life producer of battery-grade lithium carbonate, strategically located within the European EV and battery manufacturing corridor.
  • Steady-state (excluding ramp up/ramp down) production of 37,500tonnes per annum (tpa) of battery-grade lithium carbonate (Li₂CO₃), representing approximately 5.2% of EU demand in 2030[1] and sufficient for up to 1,300,000 60kWh EV batteries annually[2].
  • 26+ year operating life, underpinned by a JORC Resource of 747.54 Mt @ 0.19% Li (0.40% Li₂O ) (7.45 Mt LCE) and a JORC Reserve of 54.40 Mt @ 0.27% Li (0.58% Li₂O ) (145,000 t contained Li), with expansion optionality.
  • Robust economics based upon the first 23 years of the full LOM 27-year production schedule: (ungeared, using flat US$26,000 lithium carbonate price)[3]

o Pre-tax NPV8%: US$1.455bn (Inclusive of Grants and exclusive of inferred resources)

o Pre-tax IRR: 14.8% (Inclusive of Grants and exclusive of inferred resources)

o LOM C1 costs: US$12,621/t;

o LOM AISC: US$13,879/t

Note: PFS price assumption for lithium carbonate is based on long term incentive price which exceeds current Chinese spot price[4]

  • Initial CAPEX of US$1.72bn ((including contingency and net of approved grants) and sustaining CAPEX (life of mine) of US$0.498B.
  • Significant government support: Approval for up to EUR 360m Czech Government grant + US$36m EU Just Transition Fund grant[5].
  • DFS completion enables advancement of key workstreams:

o EU stakeholder engagement for additional grant and debt support

o Formal project financing discussions

o Finalisation of advanced off-take negotiations

European Metals Holdings Limited ("European Metals" or "the Company") announces the results of the Definitive Feasibility Study (DFS) for the Cinovec Lithium Project (Cinovec or Project), located in the Czech Republic. Cinovec hosts Europe's largest hard-rock lithium resource and one of the world's largest non-brine lithium deposits. The DFS was prepared by DRA Global (processing, including Front-End Comminution and Beneficiation (FECAB) and Lithium Chemical Plant (LCP)), Bara Consulting (mining), and specialist engineering, logistics, environmental and permitting consultants. Affiliated Czech partners, including CEZ, have also contributed extensive site, permitting, and regulatory frameworks.

The DFS builds on more than a decade of drilling and sampling, metallurgical testwork, mine design, environmental studies, permitting preparation, stakeholder engagement, infrastructure planning and engineering.

The Cinovec Project is fully located within the Czech Republic, providing EU-domestic supply of lithium to meet the continent's fast-growing requirements for EV batteries and energy-storage systems. The Project sits within 200-350 km of several gigafactories either operating, under construction, or planned within the EU and can benefit from its proximity to a large share of automotive industry entities (OEMs) in Central Europe with 22 car manufacturing plants within 400 km of Prague with over 8 million vehicles manufactured in the area annually.

Figure 1: Cinovec's location with proximity to gigafactories/OEMs either operating, under construction, or planned within the EU

Executive Chairman Keith Coughlan said:

"The DFS confirms Cinovec as one of Europe's most advanced and strategically significant lithium projects. With strong economics, central location and substantial government backing - including approval for up to EUR 360 million in Czech Government grant funding - the Project is uniquely positioned to supply long-term lithium carbonate into the European battery and EV sectors.

EMH is well placed being in partnership with CEZ, a major Czech semi-government company, and together having attracted significant European grant funding. Post this funding, the Board will continue to minimise dilution at the corporate level as it focuses on funding alternatives at the project level. Geomet, being the project company for Cinovec, will be primarily responsible for raising the early-stage funds with the majority being required towards the end of 2026. The partners are in advanced discussion with various parties with a view to provide funding to cover this requirement.

"With the DFS now released, we are advancing discussions with EU institutions regarding additional grants and strategic debt, progressing project financing with commercial lenders and potential strategic partners and moving toward the completion of off-take agreements, which are already at an advanced stage with major European battery and automotive groups. These steps collectively position Cinovec for a final investment decision."

DFS Cautionary Statement

The DFS discussed herein has been undertaken to explore the technical and economic feasibility of developing the Cinovec Lithium Project to economically and sustainably exploit the Project's Mineral Resource and Ore Reserve.

Geomet s.r.o. controls the mineral exploration licenses awarded by the Czech State over the Cinovec Lithium Project. The company is owned 49% by EMH and 51% by CEZ a.s. through its wholly owned subsidiary, SDAS. The estimated Ore Reserves and Mineral Resource underpinning the base case production target have been prepared by a Competent Person in accordance with the requirements in the JORC Code.

The Mineral Resource and Ore Reserve underpinning the estimated life of mine production under the DFS (production target) have been prepared by a competent person or persons and reported in accordance with the JORC 2012 Code. The entire processing schedule is set out over a period of 27 years, which comprises Measured and Indicated Mineral Resource (~75.5%) and Inferred Mineral Resource (~24.5%). The production target set out in this DFS covers the initial 23 years of the Processing Schedule and is based on 88% inventory within the Measured and Indicated Mineral Resources category, with 12% being classified within the Inferred Mineral Resources category. The Company has not included years 24 to 27 of the production schedule in the DFS as they are entirely based on inventory in the Inferred Mineral Resources category. There is a low level of geological confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the conversion of Inferred Mineral Resources to Indicated Mineral Resources, return the same grade and tonnage distribution, or that the production target itself would be realised. Of the Mineral Resource scheduled for extraction in this production target, ~54% is classified as Probable Ore Reserve and ~19% is classified as Proved Ore Reserve. The stated production target is based on the Company's current expectations of the future results or events and should not be solely relied upon by investors when making investing decisions. Further evaluation work and appropriate studies are required to establish sufficient confidence that this target will be met. The proportion of Inferred Mineral Resource is not a determining factor for viability of the Project.

The economic outcomes associated with the DFS are based on certain assumptions made for commodity prices, concentrate treatment and recovery charges, exchange rates and other economic variables, which are not within the Company's control and subject to change from time to time. Changes in such assumptions may have a material impact on economic outcomes.

To achieve the range of outcomes indicated in the DFS, debt and equity funding will be required. THE DFS estimates that US$2.164bn in construction capital will be required. Investors should note that there is no certainty that the Geomet s.r.o. may be able to raise the amount of funding when needed and/or reach a Final Investment Decision by the date proposed in the DFS. It is also possible that such funding may only be available on terms that may be dilutive to, or otherwise affect the value of EMH's existing shares. It is also possible that Geomet s.r.o. could pursue other 'value realisation' strategies such as a sale or partial sale of the Company's share of the Project.

Given the uncertainties involved, investors should not make any investment decisions based solely on the results of the DFS.

INTRODUCTION & DFS BACKGROUND

The Definitive Feasibility Study (DFS) for the Cinovec Lithium Project represents the culmination of more than a decade of combined geological, metallurgical, environmental, mining and engineering work undertaken by European Metals and the project operating company, Geomet s.r.o. The DFS has been prepared by DRA Global (processing, including Front-End Comminution and Beneficiation and Lithium Chemical Plant), Bara Consulting (mining) other specialist engineering groups (Dukla bulk materials handling hub, infrastructure) and multiple Czech and international environmental, permitting and logistics consultants.

The DFS consolidates:

  • Up-to-date geological interpretation supported by additional diamond drilling.
  • Expanded metallurgical programs including locked-cycle flotation campaigns and sustained pilot-scale operation of the downstream lithium chemical process.
  • Mine design and geotechnical modelling incorporating both historical mining data and contemporary laboratory testing.
  • DFS level engineering for the aerial conveyor system, Dukla bulk materials handling hub, Prunéřov beneficiation plant (FECAB), Prunéřov Lithium Chemical Plant (LCP), backfill paste plant and Doly Nástup Tušimice open pit coal mine (DNT) tailings storage facility.
  • DFS level Hydrogeological, hydrological, biodiversity, noise, vibration, air quality and visual modelling which will be utilised as part of a unified Environmental Impact Assessment (EIA).
  • A full Project Execution Plan (PEP), risk assessment, cost estimation, and implementation scheduling.

The DFS demonstrates that Cinovec is technically feasible, economically robust and strategically aligned with the European Union's objectives to internalise the supply chain for battery-grade lithium chemicals. The study confirms that all components of the proposed vertically integrated operation - from underground mining through to lithium carbonate packaging - can be constructed and operated entirely within the Czech Republic, providing security of supply to European EV and energy-storage markets.

KEY PROJECT METRICS

Key Metrics

Measured, Indicated and Inferred Resources (Mt)747.54
Proved and Probable Ore Reserves (Mt)54.40
Mine Life (Years)22.6
Production Life (Years)20.3
Annual Crusher Feed (tonnes per annum)3.2M
Total Ore - Li Grade0.27%
Li 2 CO 3 - Life of Mine Tonnes869,941
First 5 Full Production YearsYear 1Year 2Year 3Year 4Year 5
Ore Mined (million tonnes)2.542.863.203.203.21
Ore Grade (% Li₂O)0.57%0.59%0.59%0.59%0.62%
Ore Grade (%Li)0.265%0.272%0.273%0.276%0.287%
Li 2 CO 3 Tonnes per annum28,82433,58337,58038,01039,747
Project Economics (Real)
Costs (USD)LOM (000's)Li 2 CO 3 /t
Total C1 Costs9,243,49612,261
All-in-Sustaining Cost10,164,57913,879
Initial Capex2,164,8802,489
Approved Grants (US 000's)
Combined Government and Just Transition Fund463,008
Initial Capex - Grants1,701,872
Sustaining Capex498,710573
Cashflow (USD)With GrantWithout Grant
Price for Li2CO3 (USD /Tonne)26,00026,000
LOM Gross Revenue (000's)19,042,00919,042,009
LOM EBITDA (000's)9,353,7779,353,777
Pre Tax NPV (8% Disc. Rate) (000's)1,455,3681,087,897
Pre Tax IRR (8% Disc. Rate)14.8%12.5%
Post Tax NPV (8% Disc. Rate) (000's)929,396596,113
Post Tax IRR (8% Disc. Rate)12.7%10.7%

Sensitivity Analysis Results

Figure 2 - Sensitivity Analysis Tornado

Multiple hypothetical scenarios have been considered for analysing the impact to project NPV (@ 8% post- tax, nominal) by adjusting selected critical assumptions and cost inputs within a given range. The sensitivity analyses have been performed using a post-tax (nominal) discount rate of 8% with each variable as follows flexed ±X% using the midpoint price range applied as the central case. The central case assumes a Lithium Carbonate price of US$26,000/t real and results in an NPV of US$1,715M at an 8% pre-tax, nominal discount rate, with grant allowances included.

Figure 3 Graph of the mine production profile by resource category

Project Funding Sources and Strategy

EMH is well placed being in partnership with CEZ, a major Czech semi-government company, and together having attracted significant European grant funding. Post this funding, the Board will continue to minimalise dilution at the corporate level as it focuses on funding alternatives at the project level. Geomet, being the project company for Cinovec, will be primarily responsible for raising the early stage funds with the majority being required towards the end of 2026. The partners are in advanced discussion with various parties with a view to provide funding to cover this requirement.

Given the technical and economic viability demonstrated by the Feasibility Study, the Company has reasonable grounds to believe the Project could be financed via a combination of debt and equity.

Following the completion of the DFS, the Company will seek to formalise the ongoing discussions with potential debt or equity institutions. The Company expects debt could potentially be secured from a range of sources including European banks (eg EIB/KFW), Australian banks, European critical minerals funds, resource credit funds, export credit agencies, Government agencies and in conjunction with product sales or offtake agreements. The viability of the Project is enhanced by having a joint venture partner in the CEZ Group and the very clear political and economic support of the Czech Government and European Union, which will assist in negotiations for debt and equity.

The Company may also consider commencing a formal strategic partnering process whereby alternative funding options, including undertaking a corporate transaction, a joint venture partnership, a partial asset sale and/or offtake pre-payment could be undertaken if it maximises shareholder value over the long term.

The Company has maintained close contact with a number of potential offtakers in Europe and globally during the course of development of the DFS. Discussions with these parties will now be formalised.

The support of the Czech Government in the grant award is confirmation that the Cinovec Project is a foundation stone enabling the development of downstream industries, expected to bring significant industrial partners to invest in Czechia, whether in the Cinovec Project itself or the enabled Pre-CAM, CAM, Li-ion battery or BEV industries.

There is no certainty that the Company will be able to source funding as and when required. It is also possible that required funding may only be available on terms that may be dilutive to or otherwise affect the value of the Company's existing shares.

The Company has formed the view that there is a reasonable basis to believe that requisite future funding for development of the Project will be available when required based on the following:

  • EMH has a market capitalisation of approximately A$80 million and a strong track record of raising equity funding for the advancement of the Project. Approximately A$61.7M has been raised from sophisticated investors, brokers and existing shareholders, and used to advance its share of the Cinovec project;
  • The Project is Critical to European critical mineral security, with proven mining and straightforward processing methods and, once in operation, will be a significant source of lithium carbonate outside China;
  • Demand growth for lithium is expected to be strong and funding for high-quality resource projects delivering production of this metal is likely to be available. The Project has the potential to become a top-tier lithium carbonate producer within the EU and provide a strategically certain supply of lithium carbonate to gigafactories and OEM automotive suppliers all located within the European jurisdiction, which is expected to attract a range of financiers and partners;
  • Economic viability at this early stage of the Project, in a range of scenarios, has been demonstrated by strong free cashflow and a capital investment payback period of 7 years as outlined in the Feasibility Study.
  • Vulcan Energy has recently completed a fund raising for a lithium battery metal project of similar size and with a similar NPV and was able to attract a debt package of €1,185m (A$2,116m) in senior debt funding by a syndicate of 13 financial institutions comprising the European Investment Bank, five Export Credit Agencies and seven commercial banks.
  • Vulcan Energy also raised:
  • €204m in German government grants
  • €150m equity investment in Vulcan's primary German holding subsidiary, Vulcan Energie Ressourcen GmbH (GermanSubCo), by the KfW Raw Materials Fund (KfW) to acquire a 14% interest in GermanSubCo
  • €133m investment by a consortium of strategic investors comprising HOCHTIEF, Siemens Financial Services and Demeter to acquire a 15% equity interest in the Phase One Lionheart project entity With HOCHTIEF and Siemen being involved in the construction and development of the Project.

NEXT STEPS

With the DFS now complete, European Metals will proceed with the following key workstreams and accelerate Cinovec's development:

EU & Czech Government Engagement

The Company will advance discussions regarding:

  • Additional EU-level grant funding
  • Strategic debt facilities from European Investment Bank (EIB), Export Credit Agencies (ECAs) and other supranational lenders
  • Access to Critical Raw Materials Act (CRMA)-backed financing mechanisms
  • Czech co-funding structures and regional development incentives

Project Financing

The DFS provides the foundation for:

  • Formal engagement with commercial lenders
  • Due diligence by commercial lenders, EIB, ECAs and other supranational lenders
  • Evaluation of strategic partners for equity and project-level funding
  • Financial structuring scenarios that optimise cost of capital

Off-Take Agreements

The Company is engaged in advanced discussions with:

  • Major Czech and European battery manufacturers
  • Cathode active material producers
  • Automotive OEMs

With DFS parameters finalised, these discussions will progress to:

  • Binding term sheets
  • Volumetric commitments
  • Multi-year supply agreements
  • Technical qualification programmes

Environmental & Permitting

  • Submission of the Unified EIA
  • Finalisation of land-use and construction permits for all sites
  • Finalisation of water, waste, air, and operational approvals
  • Ongoing Natura 2000 and Protected Landscape Area consultations

Cinovec's location within the EU provides a significant competitive advantage for off-take partners seeking secure domestic supply.

Preparation for Final Investment Decision (FID)

FID-enabling activities include:

  • Completion of front-end engineering and design (FEED) (including contract for EPCM partner)
  • Early works packages (clearing, utilities, geotechnical groundwork)
  • Contractor prequalification
  • Detailed project execution modelling
  • Completion of full financing package

DFS OVERVIEW

PROJECT LOCATION & STRATEGIC CONTEXT

Cinovec is located in the Ústí nad Labem Region of northern Czech Republic, near the German border, and within 200-350 km of multiple operating or announced European gigafactories. The Project in its entirety comprises of 6 distinctive interconnected elements, (See Figure 3) namely:

  • Underground mine and associated surface infrastructure at a portal site, located close to Cinovec village on the Czechia / German border.
  • Aerial Conveyor System (ACS) ore transportation link running approximately 7.3km between the mine portal and an ore transfer station located at Dukla.
  • Transfer station located at the Dukla industrial site where ore is transferred from the ACS to rail and tailings material from the processing plant, destined for backfill into the mine, is transferred to the ACS to be returned to the backfill paste plant at the mine portal.
  • Rail link running 65 km between the transfer station and the processing plant.
  • The processing plant at Prunerov.
  • Tailings disposal site located on previously mined land at the Doly Nástup Tušimice coal mine (DNT) approximately 7.5km (via road) to the east of the processing plant.

The Project is positioned in one of Europe's most industrially developed regions, offering:

  • Mining construction, engineering and existing heavy industrial infrastructure and skills base experience.
  • Strong rail, road, water and energy infrastructure.
  • Proximity to major EV and battery manufacturing projects in Germany and Central and Eastern Europe.
  • Supportive state and municipal frameworks, with the Czech Republic designating Cinovec as a Strategic Deposit.
  • EU-level support through the CRMA, recognising Cinovec as a Strategic Project[6].

Cinovec therefore sits at the nexus of supply, demand and policy alignment. Its location reduces logistics risk, minimises shipment emissions, and positions the Project as a cornerstone of Europe's push to secure critical minerals within the EU.

Figure 4: Cinovec's key project components

GEOLOGY & MINERALISATION

Geological Setting

Cinovec is a greisen-hosted lithium mica deposit formed within a series of granitic intrusions. The lithium mineralisation occurs primarily within zinnwaldite-rich greisen zones that exhibit:

  • Broad lateral continuity
  • Significant thicknesses (commonly 20-100 m)
  • Predictable mineralogical behaviour
  • Favourable geotechnical conditions for large-scale underground mining

Figure 5: Longitudinal Section across the Cínovec deposit

Historical Mining

Cinovec has a long industrial history. Late 20th-century test-mining for tin in the massive Cinovec orebody extracted approximately 400,000 tonnes of lithium-bearing tin ore from small-scale test stopes, after the high tin grade hydrothermal veins coming off the massive orebody had been largely exhausted over the previous decades. This has left a legacy of drives, stopes and chambers and a wealth of geological data. The historical workings have provided:

  • Real-world geotechnical validation
  • Empirical data for rock-mass behaviour
  • Proven suitability of Sub-Level Open Stoping (SLOS)

These historical data sets significantly reduce uncertainty in the DFS mine design. The planned mine production will not mine through these historical areas, which are located above the DFS mining levels.

Mineralogical Characteristics

The dominant lithium mineral is zinnwaldite, a lithium-bearing mica with consistent metallurgical behaviour. The DFS incorporates extensive mineralogical characterisation to:

  • Define metallurgical domains
  • Predict flotation and LCP response
  • Support recovery assumptions across the mine life

RESOURCE MODEL & RESERVE BASIS

Drilling & Data Inputs

The DFS incorporates data from:

  • Historical drilling
  • Extensive new drilling by European Metals
  • Underground sampling from historical workings
  • 8.5 tonnes of bulk metallurgical samples for FECAB testwork and LCP pilot campaigns

The dataset supports a high-confidence geological and resource model.

Figure 6: Locations of the drilling at Cinovec on aerial map

Resource Estimate

The DFS Mineral Resource estimate comprises:

  • 748 Mt @ 0.19% Li
  • Containing 7.45 Mt LCE

A substantial portion is classified as Measured or Indicated, supporting DFS-level mining and processing assumptions.

Ore Reserve

The DFS mine plan is underpinned by a robust Ore Reserve that supports production in the first 22 years of the full LOM 26-year operating schedule (which included the inferred resources). Additional blocks defined within the Resource but not yet incorporated into the Reserve represent clear expansion potential beyond the base case.

Reserve estimation incorporates:

  • Geotechnical constraints
  • Mining method and design envelopes
  • Mining modifying factors
  • Metallurgical recoveries
  • Economic cut-off grade modelling

Supporting Metallurgical Testwork

Extensive metallurgical testwork using core and development rock to support and validate:

  • Mineralogy, lithology and liberation properties
  • Comminution characteristics
  • Flotation separation efficiency in terms of concentrate grade and lithium recoveries
  • Dewatering of concentrates and tailings

Bulk core samples from drilling were processed to produce sufficient concentrate for downstream pilot testwork, validating:

  • LCP extraction efficiency
  • Impurity deportment characteristics

This metallurgical dataset provides the technical foundation for both the beneficiation (FECAB) and LCP recovery assumptions adopted in the DFS.

MINING ENGINEERING & MINE DESIGN

The DFS mine design reflects the combined geological, geotechnical and operational characteristics of the Cinovec deposit. The study adopts SLOS with cemented paste-fill, supported by a robust geotechnical model informed by laboratory testing, historical mining data and numerical simulation.

Mining Method Selection

SLOS was selected following evaluation of multiple underground mining methods including room-and-pillar, cut-and-fill and drift-and-fill. Key reasons for selecting SLOS include:

  • Orebody geometry: Cinovec's thick, laterally continuous greisen zones are highly suited to bulk, long-hole stoping.
  • Rock mass competency: Laboratory and in situ testing confirm favourable rock-mass conditions.
  • Historical mine performance: Previous workings used variants of sub-level stoping with strong stability outcomes.
  • Productivity & cost: SLOS achieves the required mining rate of ~3.2 Mtpa at competitive operating cost.
  • Paste-fill compatibility: Large voids created by SLOS can be safely backfilled, enabling high extraction and geotechnical stability.

Figure 7: Underground Infrastructure - Looking North-Northeast

Stope Geometry & Design Parameters

Standard stope dimensions are optimised for stability, productivity and minimal dilution.

  • Stope height: 20 m
  • Stope width: 16 m
  • Stope length: Up to 50 m
  • Mining blocks: Four stopes vertically × five stopes horizontally, forming 80 × 80 m blocks
  • Rib pillars: 10 m
  • Sill pillars: 6 m (11 m total with ore access drives)

Figure 8: Nominal Sub-Level Stope Block & Pillar Arrangement

Mini-SLOS Stopes

Certain mineralised zones require reduced stope height to maintain stability and improve recovery:

  • Height: 7 m
  • Application: Flatter or thinner ore zones
  • Outcome: Increased recovery of marginal domains without compromising safety

Mine Layout & Infrastructure

The mine is accessed via a Twin Decline System:

  • One decline dedicated to vehicle access, services, water, power distribution, ventilation intake
  • One decline dedicated to the conveyor, forming the mine's primary materials handling backbone

Figure 9: Twin decline system

Internal Mine Development

  • Spiral ramps accessing multiple mining horizons
  • Ore drives positioned on sub-levels
  • Cross-cuts enabling multiple operating fronts
  • Ventilation raises and emergency egress

Figure 10: Access ramps / Drives and LHOS / Rib Pillar Ore Drives

Ventilation & Airflow Modelling

The mine uses a push-pull ventilation system designed to:

  • Maintain statutory airflow
  • Control dust and diesel particulates
  • Provide redundancy for fan outages
  • Operate under varying seasonal temperature conditions

Computational fluid dynamics (CFD) modelling is integrated into the DFS.

Production Schedule

The DFS production plan is structured to provide:

  • Early development ore for commissioning
  • Ramp-up to full production over multiple years
  • Steady-state ore production: ~3.2 Mtpa
  • Multiple mining fronts to maintain schedule resilience
  • Optimised sequencing for geotechnical stability and paste-fill curing

Paste-fill System

Paste-fill forms a critical part of the mine design.

Paste-fill characteristics:

  • Blend of tailings, cement and water
  • Engineered to achieve required strength and curing performance
  • Returned underground via the rail and subsequently via the aerial conveyor system

Benefits:

  • Maximises ore extraction
  • Minimises surface tailings footprint
  • Enhances ground stability
  • Reduces long-term geotechnical risk

MATERIALS HANDLING & LOGISTICS

Cinovec employs an integrated materials-handling system linking underground operations with surface processing infrastructure.

Underground Crushing & Conveyor Feed

Primary and secondary crushing underground reduces ore to <83 mm, enabling efficient feeding to the conveyor decline. Benefits include:

  • Reduced truck traffic
  • Lower diesel consumption
  • Reduced dust and noise
  • More consistent feed to the Aerial Conveyor System

Figure 11: Underground Crushing Arrangement within Crushing Chambers

Aerial Conveyor System

A defining feature of Cinovec is the bi-directional aerial conveyor, engineered to transport ore from the mine portal to Dukla and return tailings materials to the backfill paste plant at the mine portal area.

Engineering Characteristics

  • Designed for operation in snow, ice and high winds
  • Tower spacing optimised for topography and visual impact
  • Low-noise drive systems
  • Enclosed belt structure to minimise dust
  • Passive and active environmental controls

Environmental Advantages

  • Eliminates heavy trucking through local villages
  • Reduces emissions and traffic congestion
  • Minimises ground disturbance
  • Aligns with Natura 2000 and Protected Landscape Area constraints

Figure 12: Aerial Conveyor example

Dukla Materials Handling Hub

Dukla is the operational centre for ore and tailings backfill receipt, stockpiling and rail transport.

Features:

  • Large Run of Mine (ROM) and tailings stockpiles
  • Bucket-wheel reclaimer for consistent blending
  • Rail loadout system sized for the Prunéřov processing rate
  • Tailings reception system feeding the Aerial Conveyor System (ACS)
  • Water and utility infrastructure

Dukla's location leverages existing industrial permissions and rail infrastructure, lowering both CAPEX and permitting complexity.

Rail Logistics

Ore is transported ~65 km to Prunéřov via existing freight rail networks.

Benefits:

  • Low emissions
  • Predictable year-round operation
  • Quiet and low-impact compared to road haulage
  • Leverages established Czech rail infrastructure

Figure 13: Plan view of the Dukla site

Figure 14: Aerial view of Dukla

PROCESSING - FRONT-END COMMINUTION & BENEFICIATION (FECAB)

The Cinovec beneficiation flowsheet has been refined over several years of laboratory testing.

Comminution Circuit

The FECAB plant comprises:

  • Underground crushing (<83 mm)
  • Surface tertiary crushing and screening
  • Rod milling to achieve optimal liberation with minimal slimes, and classification
  • Desliming to prepare feed for flotation

Beneficiation Circuit

Flotation is the primary method selected for concentrating zinnwaldite. The circuit includes:

  • Rougher flotation
  • Two stages of cleaning flotation
  • Scavenger flotation stages to optimise recovery
  • Concentrate thickening and filtration
  • Tailings thickening and filtration

DFS testing demonstrates:

  • Flotation has high selectivity for Zinnwaldite, hence efficient concentration
  • Consistent high purity concentrate grades: >1.44% Li
  • Concentrate mass yields of 17-20% (in terms of ROM) realising a 5 times mass reduction
  • Stable FECAB lithium recoveries: >89%

Figure 15: Flotation Process

PROCESSING - LITHIUM CHEMICAL PLANT

The LCP comprises:

  • Mixing of concentrate with simple roast reagents gypsum, limestone, recycled alkali sulphates
  • Pellet extrusion, roasting for 1 hour at 925°C and water leach at 60°C
  • Impurity removal steps - transition metals, calcium
  • Lithium phosphate precipitation and dissolution to give lithium sulphate solution
  • Glauber's salt crystallisation to give minor by-product stream and alkali sulphates to recycle to roast
  • Crude lithium precipitation
  • Bicarbonation and micronisation to give battery-grade lithium carbonate

DFS testing demonstrates:

  • Consistent battery grade lithium carbonate meeting current international standards
  • Stable LCP lithium recoveries: ~91%
  • Reliable performance across metallurgical domains

Figure 16: Aerial View of the Processing plant complex at Prunerov

Combined FECAB and LCP testwork supports an overall lithium recovery of approximately 80.7% into battery-grade lithium carbonate, consistent with the DFS flowsheet design.

Figure 17: LCP - Rotary Kilns

Flowsheet Evolution & Testwork

Earlier flowsheets included WHIMS (magnetic separation). However, systematic testwork showed:

  • WHIMS performance declines with fines (<150 µm)
  • Overall recovery improves with flotation-only flowsheets
  • Simpler flowsheet reduces CAPEX and OPEX

Subsequent laboratory testwork including locked-cycle flotation validated the final flowsheet.

Concentrate Quality & Handling

The final concentrate is:

  • Dewatered to specification
  • Stockpiled at Prunéřov
  • Fed directly into the LCP roasting step

Variability testing confirms suitable performance across head grades ranging from ~0.19% to ~0.35% Li.

Figure 18: Overall Process Schematic

ENVIRONMENTAL, SOCIAL & GOVERNANCE (ESG)

The DFS embeds ESG principles across all mine, transport, and processing design elements. Cinovec has been structured to meet or exceed the requirements of:

  • Czech national and regional environmental laws
  • EU CRMA
  • International Finance Corporation Performance Standards
  • Equator Principles
  • EBRD Environmental & Social Guidelines

ESG considerations have shaped process flowsheet selection, materials handling design, logistics routing, energy sourcing, community engagement, closure planning, and environmental monitoring systems.

Environmental Impact Assessment (Unified EIA)

Cinovec is progressing a unified and fully integrated Environmental Impact Assessment, covering all major project components and expected to be submitted in December 2025. it covers:

  • Underground mine
  • Aerial Conveyor System
  • Dukla materials handling and rail hub
  • Prunéřov FECAB and LCP complexes
  • DNT tailings and backfill facility

A single EIA reduces duplication, streamlines regulatory oversight, and ensures cumulative impacts are assessed holistically.

Key EIA components include:

  • Air quality & dust modelling
  • Noise & vibration modelling
  • Visual and landscape assessments
  • Biodiversity surveys and habitat mapping
  • Water quality modelling
  • Groundwater interactions
  • Waste, effluent and spill management plans
  • Natura 2000 compliance assessment

Biodiversity & Natura 2000 Compatibility

Cinovec occurs near areas of biodiversity sensitivity, including:

  • Natura 2000 sites (protected habitats under EU law)
  • Spa-regions with protected water resources
  • Landscapes under conservation designation

DFS-aligned environmental management measures include:

  • No surface mining
  • Minimised land clearing and disturbed footprint
  • ACS alignment refined to avoid harm to protected zones
  • Enclosed conveyor system to eliminate dust and reduce noise
  • Wildlife movement corridors maintained
  • Detailed flora and fauna baseline surveys completed

The DFS concludes the Project can operate without unacceptable impacts on Natura 2000 values.

Air Quality, Noise, and Vibration

Air Quality

Use of enclosed conveyors, underground crushing and rail transport significantly reduces dust emissions. Prunéřov's existing industrial monitoring infrastructure supports continuous air-quality assessment.

Noise

Noise modelling confirms compliance with Czech and EU thresholds at residential receptors. Key controls include:

  • Low-noise conveyor drives
  • Acoustic shielding
  • Rail-loadout timing restrictions (if required)

Vibration

Modelling covers blasting, ACS tower construction and rail operations. Peak vibration levels are well within regulatory limits.

Water Management & Hydrogeology

DFS hydrological and hydrogeological studies confirm:

  • Minimal interaction between mine voids and regional aquifers
  • Water balance managed through closed-loop systems
  • Non-contact water diverted away from operational areas
  • Lined systems at Dukla, Prunéřov and DNT to control seepage
  • Treatment plants comply with Czech water discharge standards

Tailings that are not reused as underground paste-fill will be stored in a designed filtered dry-stack facility at DNT, further reducing the Project's long-term surface footprint.

Protection of spa water systems - a critical regional concern - is fully incorporated into the DFS and EIA.

Social Impact & Stakeholder Engagement

Selection of the Prunéřov processing complex followed extensive community and stakeholder consultation, with the location optimised to minimise impacts on inhabited areas.

European Metals and Geomet have conducted extensive engagement over several years with:

  • 17 municipalities
  • Spa-town authorities (Teplice, Dubí)
  • Regional Ústí nad Labem authorities
  • National ministries (Industry & Trade, Environment, Transport, Finance)
  • Local community representatives
  • Environmental groups
  • Transport and infrastructure agencies

Key outcomes include:

  • Route optimisation for ACS to avoid sensitive viewpoints
  • Traffic minimisation through elimination of ore haulage trucks
  • Information centres and consultation sessions
  • Integration of local employment and supply-chain development plans

Climate, Carbon & Energy Strategy

Cinovec's design reduces carbon intensity through:

  • Elimination of diesel truck haulage
  • Rail-based logistics
  • Underground crushing and conveying
  • Ability to utilise increasing Czech grid renewable penetration
  • Energy-efficient roasting and drying systems
  • Waste heat recovery opportunities

A ISO-compliant lifecycle assessment is being finalised for the EIA.

PERMITTING, APPROVALS & GOVERNANCE

Cinovec benefits from streamlined approvals pathways due to its designation as:

  • A Strategic Project under the EU CRMA
  • A Strategic Deposit under Czech law

These classifications support accelerated permitting, access to EU funding structures, priority regulatory engagement and governance stability.

Permitting Framework

The Project requires the following major approvals:

  • Unified EIA approval
  • Land-use and zoning confirmations
  • Construction permits (mine, ACS, Dukla, Prunéřov, DNT)
  • Mining licence and extraction permit
  • Rail-loading and transport licences
  • Air, water, and waste management permits
  • Operational safety approvals

The EIA is the critical path approval, with all other major permits contingent on its issuance.

Government Support

The Project has received:

  • Approval for up to EUR 360m from the Czech Government, representing up to 26% of eligible capital costs.
  • US$36m grant from the EU JTF, targeted toward regional economic transformation.

Additional EU-level debt or hybrid instruments may be available through:

  • EIB
  • ECAs
  • European Commission's Innovation Fund

DFS completion enables formal engagement with these institutions.

EU CRMA

The Project has been formally recognised by the European Commission under the CRMA, enabling streamlined permitting pathways and reinforcing the Project's importance to Europe's battery supply chain.

Cinovec's CRMA designation provides:

  • Accelerated permitting timelines
  • Access to strategic funding structures
  • Priority regulatory processing
  • Enhanced visibility among EU industry and policy groups
  • Recognition as a project of "strategic importance for green transition"

Governance & Risk Management

DFS includes a full Quantitative Risk Assessment (QRA) covering:

  • Technical risks
  • Schedule risks
  • Market risks
  • Environmental and permitting risks
  • Operational readiness
  • Supply chain and workforce availability

Mitigation measures include:

  • Staged procurement planning
  • Early works design packages
  • All-season construction methodologies
  • Redundancy in critical equipment
  • Conservative ramp-up modelling

ECONOMIC RESULTS & FINANCIAL ANALYSIS

The DFS demonstrates strong economic outcomes with a long-life, low-cost operation and substantial revenue potential.

Key DFS Economic Outcomes

  • Pre-tax NPV (8%): US$1.455bn (Post-tax NPV: US$929m) (inclusive of approved Grants but exclusive of inferred resources)
  • Pre-tax IRR: 14.8% (Post-tax IRR: 12.7%)(inclusive of approved Grants but exclusive of inferred resources)
  • Payback period: ~7 years starting from production start date
  • LOM Revenue: US$19,042bn
  • LOM C1 Costs: US$12,621/t Li₂CO₃
  • LOM AISC: US$13,879/t Li₂CO₃
  • Initial CAPEX US$2.164bn; Sustaining CAPEX US$0.498bn (inclusive of contingency) but excluding Grants (Initial CAPEX US$1.72bn net of Approved Grants)

Capital Cost Breakdown

CAPEX includes:

  • Underground mine development
  • ACS construction and instrumentation
  • Dukla foundations, stockpiling and rail-loadout infrastructure
  • FECAB plant build at Prunéřov
  • LCP construction
  • DNT facility earthworks, lining, pumping and monitoring
  • Power, water, gas and access infrastructure
  • Owner's costs, EPCM (engineering, procurement and construction management), spares, commissioning and contingency

Grant support (Czech Government + EU Just Transition Fund (JTF)) significantly reduces net capital requirements.

Operating Cost Structure

OPEX is driven by:

  • Mine production and maintenance
  • Paste-fill operations
  • ACS power consumption
  • Rail logistics
  • FECAB reagent and comminution costs
  • LCP roasting, leaching and purification reagents
  • Labour, utilities, and general and administrative costs

Cinovec's OPEX reflects:

  • Short logistics distances
  • Efficient rail utilisation
  • No truck haulage
  • Use of existing industrial land at Prunéřov
  • Stable power and water costs in Czech Republic

Product Marketing & Off-Take Position

European Metals is in advanced negotiations with major:

  • European battery manufacturers
  • Cathode producers
  • Automotive OEMs

DFS completion enables conversion of these discussions into binding off-take agreements.

Funding and Strategic Partnerships

DFS-level financial modelling supports engagement with:

  • EU institutions offering strategic debt
  • ECAs
  • Commercial banks
  • Potential strategic equity partners
  • Government-backed lending instruments

The Project's CRMA classification is a critical enabler of funding optionality.

PROJECT EXECUTION PLAN

The DFS defines an execution schedule commencing in early 2026, with underground development, ACS and Dukla construction and Prunéřov FECAB/LCP builds sequenced through to integrated commissioning in 2031.

Construction Strategy

Cinovec adopts a multi-stage construction approach designed to:

  • Minimise schedule risk
  • Enable early works to accelerate project readiness
  • Align commissioning across multiple sites
  • Utilise regional contractors familiar with industrial builds

Major execution components:

Underground Mine Development

o Advance declines and establish the primary conveyor drive chambers

o Install early ventilation infrastructure

o Develop initial stoping panels for commissioning ore

Aerial Conveyor System (ACS) Construction

o Tower-by-tower foundation installation

o Cable-stringing and mechanical installation

o Winterisation and all-weather performance validation

Dukla Hub Construction

o Groundworks and utility relocation (including gas pipeline adjustments)

o ROM pad creation and reclaimer installation

o Rail siding and loadout system construction

Prunéřov Beneficiation (FECAB) & LCP Construction

o Site clearing and regrading

o Shared utilities build-out

o Sequential construction of FECAB followed by LCP

o Integrated commissioning plan

DNT Tailings Facility Preparation

o Void shaping and lining

o Construction of return-water, drainage and monitoring systems

o Paste-fill distribution lines

Procurement & Contracting Strategy

Procurement is structured to balance local participation with the delivery certainty of international OEMs.

DFS-aligned procurement approach:

  • Long-lead items (kilns, mills, flotation cells, crystallisers) prioritised for early commitment
  • Modularisation of key structures to speed on-site assembly
  • Local Czech contractors used for civil works, electrical, mechanical installation and site utilities
  • Competitive tendering across all major plant packages
  • Framework agreements for reagents, maintenance consumables and spare parts

This strategy reduces schedule bottlenecks, enhances local content, and supports stable long-term operations.

Workforce & Training Strategy

DFS modelling incorporates:

  • Required workforce of ~1,200 direct construction jobs
  • ~700 operational roles across mining, processing, logistics, laboratory, maintenance and administration
  • Targeted hiring from local municipalities
  • Specialist training programmes for LCP operations
  • Partnerships with regional technical universities and vocational schools

Operational Readiness & Ramp-Up

The DFS includes a detailed project schedule:

  • Commissioning of FECAB to deliver consistent concentrate feed
  • Stepwise activation of LCP roasting, leaching, purification and crystallisation circuits
  • Achievement of design throughput over a multi-year ramp-up period
  • Multi-front mining approach ensuring reliable feed to processing operations

Risk Management & QRA Outcomes

A full QRA covers technical, economic, environmental, and execution risks.

Mitigations incorporated into the DFS include:

  • Conservative equipment sizing and redundancy
  • Detailed geotechnical modelling
  • Advanced ACS climatic modelling (icing, snow load, wind)
  • Multisource power stability analysis
  • Supply-chain redundancy for critical reagents
  • Construction season planning for winter conditions
  • Flexible scheduling to accommodate EIA timing risks

CLOSING STATEMENT

The Definitive Feasibility Study confirms Cinovec as a long-life, high output and strategically important lithium project capable of delivering substantial volumes of battery-grade lithium carbonate into the European supply chain.

Cinovec's combination of:

  • Scale and longevity
  • Robust economics
  • Proximity to EU gigafactories
  • Vertically integrated design
  • Strong government and regulatory support
  • Advanced off-take and funding discussions

positions it as one of the most strategically significant lithium developments globally.

European Metals will continue to work closely with its stakeholders, regulatory authorities, EU institutions, financing partners and future customers to advance the Project towards construction and production.

DFS -SUMMARY

The summary of the DFS and JORC Table is contained in the following link:

This announcement has been approved for release by the Board.

CAUTION REGARDING FORWARD LOOKING STATEMENTS

LITHIUM CLASSIFICATION AND CONVERSION FACTORS

Lithium resources and reserves are usually presented in tonnes of LCE or Li.

The standard conversion factors are set out in the table below:

Table: Conversion Factors for Lithium Compounds and Minerals

Convert fromConvert to LiConvert to Li 2 OConvert to Li 2 CO 3Convert to LiOH.H 2 O
LithiumLi1.0002.1535.3256.048
Lithium OxideLi 2 O0.4641.0002.4732.809
Lithium CarbonateLi 2 CO 30.1880.4041.0001.136
Lithium HydroxideLiOH.H 2 O0.1650.3560.8801.000
Lithium FluorideLiF0.2680.5761.4241.618

[1] https://miningdigital.com/news/evs-batteries-how-much-lithium-is-needed-to-decarbonise

[2] https://www.iea.org/reports/global-ev-outlook-2025/electric-vehicle-batteries / https://gycxsolar.com/understanding-lithium-content-in-a-1-kwh-battery-benefits-for-stackable-lithium-batteries-systems/#How_Much_Lithium_Is_There

[3] Price assumption of $26,000/t battery grade lithium carbonate (99.5% battery grade) based Fastmarket Global's long term forecast (Q3 2025 presentation)

[4] See DFS cautionary statement below for further details

[5] ASX/ AIM releases dated 28 April 2025 and 28 November 2025

[6] See ASX/AIM Announcement dated 26 March 2025

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note