Quarterly Report March 2025
Exploration drilling at Conchas project returned positive lithium and rubidium results; arbitration against Spain progresses.
- Cash reserves A$78 million
- Debt None
- RC drill holes completed 33
- Best lithium intercept 14m @ 0.95% Li2O & 0.39% Rb2O
- Arbitration claim against Spain US$1 billion
Select text to share a quote on X · sign in to keep highlights & notes in your BKY notes
| NEWS RELEASE | 30 April 2025 |
Quarterly Report March 2025
Summary:
Exploration at Conchas Project
During the quarter, Berkeley Energia Limited ( Berkeley or Company ) announced the results of a reverse circulation ( RC ) and diamond drilling program completed at the Conchas project ( Conchas Project ), as part of its ongoing exploration initiative targeting critical minerals in Spain.
Highlights included:
- Assay results demonstrated shallow, thick zones of lithium and rubidium mineralisation, hosted within a muscovitic leucogranite, intersected in all 33 RC holes.
- Drill intercepts include:
o 14m @ 0.95% Li 2 O & 0.39% Rb 2 O (from 40m)
o 18m @ 0.55% Li 2 O & 0.23% Rb 2 O (from surface)
o 61m @ 0.50% Li 2 O & 0.21% Rb 2 O (from surface)
o 27m @ 0.44% Li 2 O & 0.21% Rb 2 O (from surface)
o 56m @ 0.48% Li 2 O & 0.21% Rb 2 O (from surface)
- Samples from an additional three diamond holes completed in the drill program have been sent for preliminary metallurgical test work with results anticipated in the June 2025 quarter.
- Next steps include 3D modelling of the drilling data and completion of the preliminary metallurgical test work program.
- International Arbitration against Spain
As part of its Request, BEL alleges that Spain's actions against BME and the Salamanca project ( Salamanca Project ) have violated multiple provisions of the Energy Charter Treaty ( ECT ), and that BEL is seeking preliminary compensation in the order of US$1 billion (US$1,000,000,000) for these violations.
During the quarter, the Tribunal was formally constituted with the first tribunal session to be held in early May 2025, where the timetable and arbitration rules will be established.
Spanish Nuclear Power Industry:
During and subsequent to the end of the quarter, there have been a number of important recent developments regarding the nuclear industry in Spain, including:
- Proposal to Reverse Spain's Nuclear Phase-out Approved by Parliament
o A Plenary Session of the Spanish Congress has approved a non-law proposal calling for the government to implement a series of measures that would reverse the country's decision to phase out nuclear power. Under current plans, Spain's power reactors are all scheduled to shut between 2027 and 2035. The proposal, presented by the right-wing People's Party ( PP ), was passed in February 2025. This non-law proposal is not binding but urges the Spanish Government to consider its content.
o Subsequently, in early April, the PP registered a bill in the Congress to extend the useful life of Spanish nuclear power plants. The bill has been registered by the Spanish Congress and sent to the Government for their comments and response due late May 2025.
Demonstrations
o Approximately 7,000 people attended a demonstration against the planned closure of the Almaraz nuclear power plant in Extremadura as part of the country's nuclear phase out policy. The demonstration was called by the municipalities in the area of influence of the Almaraz nuclear power plant and the citizens' platform "Yes to Almaraz, Yes to the Future" to demand the continuation of the activity of the Extremadura plant in light of the closure planned by the central government.
Nuclear Power Plant Continuation
o One of Spain's nuclear operators, said it has received notification of the ministerial order extending the operating permit for the Trillo nuclear power plant until November 2034. The Ministry for Ecological Transition and the Demographic Challenge ( MITECO ) had considered the favourable report issued on by the Nuclear Safety Council ( NSC ) in its decision to grant the operating extension.
Nuclear Industry Manifesto
The manifesto - signed by 32 companies, including Empresarios Agrupados-GHESA (EAG), Framatome, GDES, GE Vernova, IDOM and Westinghouse - says: "We urge the initiation of a dialogue and renegotiation of the 2019 agreement on the phased shutdown of nuclear power plants. This agreement was made under an industrial, geopolitical, social and economic context that is vastly different from today's reality."
Balance Sheet
The Company is in a strong financial position with A$78 million in cash reserves and no debt.
Figure 1: Location of the Salamanca Project, Spain
Salamanca Project Update
Berkeley has been awarded with the Carbon Neutrality Certificates for the years 2020, 2021, and 2022, by MITECO. This represents an important step in the Company's journey to combat climate change and continue contributing to sustainability.
To achieve this goal, 329 trees have been planted within the reforestation project in the public utility forest area of the Monte del Catálogo de Utilidad Pública in the province of Ávila, No. 13 "El Pinar," located in the municipality of Mijares.
These trees will absorb a total of 56 tons of CO2, a quantity expected over a 40-year period according to the reference values from the MITECO Registry. The species planted include Scots pine, birch, rowan, yew, and holly.
Thus, Berkeley, in its commitment to fighting climate change, contributes to the following Sustainable Development Goals:
Exploration
During the quarter, the Company continued with its exploration program focusing on critical minerals in Spain. The exploration initiative is targeting lithium, rubidium, tin, tantalum, niobium, tungsten, and other battery and critical metals, within the Company's existing tenements in western Spain that do not form part of Berkeley's main undertaking being the development of the Salamanca Project.
Conchas Project
Figure 2: IP Conchas Location Plans and Geology / Drill Hole Location Plan
The drill program comprised five broad spaced RC holes for a total of 282m. Anomalous results for lithium (Li), tin (Sn), rubidium (Rb), cesium (Cs), niobium (Nb) and tantalum (Ta) obtained from multi-element analysis of drill samples were reported in April 2023, demonstrating Conchas' exploration potential for several critical and strategic raw materials included in the European Commission's Critical Raw Materials Act (CRMA). The drill results included 25m @ 0.56% Li2O and 0.22% Rb2O from surface (CCR0002).
2024 Drilling Program
| Hole No. | Down Hole Intercept | From Depth (Down Hole) |
| CCR006 | 27m @ 0.44% Li 2 O & 0.21% Rb 2 O 14m @ 0.95% Li 2 O & 0.39% Rb 2 O | surface 40m |
| CCR011 | 55m @ 0.31% Li 2 O & 0.18% Rb 2 O | surface |
| CCR012 | 61m @ 0.50% Li 2 O & 0.21% Rb 2 O | surface |
| CCR017 | 18m @ 0.55% Li 2 O & 0.23% Rb 2 O | surface |
| CCR025 | 56m @ 0.48% Li 2 O & 0.21% Rb 2 O | surface |
| CCR033 | 19m @ 0.35% Li 2 O & 0.21% Rb 2 O | surface |
- the mineralised muscovite leucogranite is very homogeneous in terms of mineralogy
- the southern zone of mineralisation contains the highest grades overall, with individual assay values exceeding 2.5% Li 2 O. In this area, all holes penetrated the host muscovitic leucogranite and ended in the underlying regional granite (Figure 3)
- In the northeast, the muscovite leucogranite is significantly thicker (>169m in CCR020) and all holes returned Rb 2 O grades exceeding 1,000ppm (Figure 4) however, Li 2 O grades are lower than in the south and northwest areas
- Drilling in the northwest recorded the highest grades of both Li 2 O and Rb 2 O, as well as the highest grades of other elements
Figure 3: IP Conchas 4,492,225 North Cross Section
Figure 4: IP Conchas 4,492,925 North Cross Section
Next Steps
Representative samples obtained from the three diamond core holes drilled in the 2024 program have been sent to the Oviedo School of Mines' (Spain) and Wardell Armstrong International's (England) laboratories for preliminary metallurgical test work.
The metallurgical test work programs have been designed to assess the potential recovery of Li, Rb and the other elements of economic interest, and comprise crushing and grinding (bond index calculation), gravity (jigs, shaking tables and multi gravity separator), high intensity wet and dry magnetic separation on the concentrates, froth flotation, and characterisation of the samples.
Various workstreams have advanced during the quarter, with results of the metallurgical test work programs anticipated in the June 2025 quarter.
3D modelling of the drilling data is also being undertaken to refine the geological interpretation and assess volumes, average grades and grade distributions for the Li and Rb mineralisation at different cut-offs.
Rubidium1,2,3,4,5
Rubidium is a critical raw material with growing significance in advanced technology and industrial applications, including in the defence and military, aerospace, communications, biomedical and renewable energy sectors.
Oliva and La Majada Projects
An updated Exploration Program for the La Majada Project, together with the birdlife study and rehabilitation plan, have been submitted to the relevant authorities during the quarter. The Exploration Program was updated to align it to new legislation recently introduced for the Castilla La Mancha Region.
International Arbitration Dispute
In May 2024, the Company's wholly owned subsidiary, Berkeley Exploration Limited (BEL), filed a Request for Arbitration (Request) for its investments in Spain through its Spanish subsidiary, Berkeley Minera España SA (BME), initiating arbitration proceedings against the Kingdom of Spain (Spain) before International Centre for Settlement of Investment Disputes (ICSID).
As part of its Request, BEL alleges that Spain's actions against BME and the Salamanca Project have violated multiple provisions of the Energy Charter Treaty (ECT), and that BEL is seeking preliminary compensation in the order of US$1 billion (US$1,000,000,000) for these violations.
The Request was submitted by BEL's arbitration lawyers based in Spain. Subsequent to the quarter, BEL agreed an engagement letter with its lawyers to provide ongoing arbitration services on a reduced and capped fee basis that also includes a three percent success fee which is capped and is only payable to the lawyers in the event of a successful award and if monetary damages are received by BEL.
Previously, BEL received the Notice of Registration from ICSID with the Registration of the Arbitration published on the ICSID website. During the quarter, the Tribunal was formally constituted with the first tribunal session to be held in early May 2025, where the timetable and arbitration rules will be established.
Background to Dispute
Competent Persons Statements
References
1 www.mordorintelligence.com/es/industry-reports/rubidium-market
2 www.straitsresearch.com/report/rubidium-market
3 www.marketresearchfuture.com/reports/rubidium-market-27298
4 U.S Geological Survey, Mineral Commodity Summaries, January 2024 - Rubidium
5 www.usgs.gov/news/national-news-release/us-geological-survey-releases-2022-list-critical-minerals
Appendix 1: Mineral Resource at Salamanca
| Deposit Name | Resource Category | Tonnes (Mt) | U 3 O 8 (ppm) | U 3 O 8 (Mlbs) |
|---|---|---|---|---|
| Retortillo | Measured | 4.1 | 498 | 4.5 |
| Indicated | 11.3 | 395 | 9.8 | |
| Inferred | 0.2 | 368 | 0.2 | |
| Total | 15.6 | 422 | 14.5 | |
| Zona 7 | Measured Indicated | 5.2 10.5 | 674 761 | 7.8 17.6 |
| Inferred | 6.0 | 364 | 4.8 | |
| Total | 21.7 | 631 | 30.2 | |
| Alameda | Indicated | 20.0 | 455 | 20.1 |
| Inferred | 0.7 | 657 | 1.0 | |
| Total | 20.7 | 462 | 21.1 | |
| Las Carbas | Inferred | 0.6 | 443 | 0.6 |
| Cristina | Inferred | 0.8 | 460 | 0.8 |
| Caridad | Inferred | 0.4 | 382 | 0.4 |
| Villares | Inferred | 0.7 | 672 | 1.1 |
| Villares North | Inferred | 0.3 | 388 | 0.2 |
| Total Retortillo Satellites | Total | 2.8 | 492 | 3.0 |
| Villar | Inferred | 5.0 | 446 | 4.9 |
| Alameda Nth Zone 2 | Inferred | 1.2 | 472 | 1.3 |
| Alameda Nth Zone 19 | Inferred | 1.1 | 492 | 1.2 |
| Alameda Nth Zone 21 | Inferred | 1.8 | 531 | 2.1 |
| Total Alameda Satellites | Total | 9.1 | 472 | 9.5 |
| Gambuta | Inferred | 12.7 | 394 | 11.1 |
| Salamanca Project Total | Measured | 9.3 | 597 | 12.3 |
| Indicated | 41.8 | 516 | 47.5 | |
| Inferred | 31.5 | 395 | 29.6 | |
| Total (*) | 82.6 | 514 | 89.3 |
Appendix 2: Summary of Mining Tenements
As at 31 March 2025, the Company had an interest in the following tenements:
| Location | Tenement Name | Percentage Interest | Status |
|---|---|---|---|
| Spain | |||
| Salamanca | D.S.R Salamanca 28 (Alameda) | 100% | Granted |
| D.S.R Salamanca 29 (Villar) | 100% | Granted | |
| I.P. Abedules | 100% | Granted | |
| I.P. Abetos | 100% | Granted | |
| I.P. Alcornoques | 100% | Granted | |
| I.P. Alisos | 100% | Granted | |
| I.P. Bardal | 100% | Granted | |
| I.P. Barquilla | 100% | Granted | |
| I.P. Berzosa | 100% | Granted | |
| I.P. Campillo | 100% | Granted | |
| I.P. Casta ñ os 2 | 100% | Granted | |
| I.P. Ciervo | 100% | Granted | |
| I.P. Conchas | 100% | Granted | |
| I.P. Dehesa | 100% | Granted | |
| I.P. El Á guila | 100% | Granted | |
| I.P. El Vaqueril | 100% | Granted | |
| I.P. Espinera | 100% | Granted | |
| I.P. Horcajada | 100% | Granted | |
| I.P. Lis | 100% | Granted | |
| I.P. Mailleras | 100% | Granted | |
| I.P. Mimbre | 100% | Granted | |
| I.P. Pedreras | 100% | Granted | |
| C á ceres | I.P. Almendro E.C. Gambuta | 100% 100% | Granted^ Pending^ |
| I.P. Ibor | 100% | Granted | |
| I.P. Olmos | 100% | Granted | |
| Badajoz | I.P. Los Bélicos | 100% | Granted** |
| I.P.A. Ampliación Los Bélicos | 100% | Pending** | |
| Ciudad Real | I.P.A. La Majada | 100% | Pending** |
^The Company has applied for an Exploitation Concession from the existing IP Almendro.
**Exploracion de Recuros Minerales S.L.U (ERM), a wholly owned subsidiary of the Company, has entered into a Tenement Sale and Purchase Agreement and Royalty Deed to acquire IP Los Bélicos, IPA Ampliación Los Bélicos, and IPA La Majada.
Appendix 3: Related Party Payments
During the quarter ended 31 March 2025, the Company made payments of $94,000 to related parties and their associates. These payments relate to existing remuneration arrangements (director and consulting fees plus statutory superannuation).
Appendix 4: Exploration and Mining Expenditure
During the quarter ended 31 March 2025, the Company made the following payments in relation to exploration and development activities:
| Activity | A$000 |
|---|---|
| Permitting related expenditure (including legal costs) | 429 |
| Drilling related costs | 283 |
| Assay costs, radiological protection and monitoring | 31 |
| Consultants and other expenditure | 259 |
| Payment/(return) of VAT and other social taxes in Spain | (220) |
| Total as reported in the Appendix 5B | 782 |
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Berkeley Energia Limited
| (b) ABN | (c) Quarter ended ("current quarter") | ||
| 40 052 468 569 | 31 March 2025 | ||
| Consolidated statement of cash flows | Current quarter $A'000 | Year to date (9 months) $A'000 | |
| 1. | Cash flows from operating activities | - | - |
| 1.1 | Receipts from customers | ||
| 1.2 | Payments for | (782) | (2,405) |
| (a) exploration & evaluation | |||
| (b) development | - | - | |
| (c) production | - | - | |
| (d) staff costs | (327) | (1,064) | |
| (e) administration and corporate costs | (210) | (810) | |
| 1.3 | Dividends received (see note 3) | - | - |
| 1.4 | Interest received | 697 | 2,340 |
| 1.5 | Interest and other costs of finance paid | - | - |
| 1.6 | Income taxes paid | - | - |
| 1.7 | Government grants and tax incentives | - | - |
| 1.8 | Other (provide details if material) (a) Business Development (b) Arbitration related expenses | (88) - | (201) (1,298) |
| 1.9 | Net cash from / (used in) operating activities | (710) | (3,438) |
| 2. | Cash flows from investing activities | - | - |
| 2.1 | Payments to acquire or for: | ||
| (a) entities | |||
| (b) tenements | - | - | |
| (c) property, plant and equipment | - | - | |
| (d) exploration & evaluation | - | - | |
| (e) investments | - | - | |
| (f) other non-current assets | - | - | |
| 2.2 | Proceeds from the disposal of: | - | - |
| (a) entities | |||
| (b) tenements | - | - | |
| (c) property, plant and equipment | - | - | |
| (d) investments | - | - | |
| (e) other non-current assets | - | - | |
| 2.3 | Cash flows from loans to other entities | - | - |
| 2.4 | Dividends received (see note 3) | - | - |
| 2.5 | Other (provide details if material) | - | - |
| 2.6 | Net cash from / (used in) investing activities | - | - |
| 3. | Cash flows from financing activities | - | - |
| 3.1 | Proceeds from issues of equity securities (excluding convertible debt securities) | ||
| 3.2 | Proceeds from issue of convertible debt securities | - | - |
| 3.3 | Proceeds from exercise of options | - | - |
| 3.4 | Transaction costs related to issues of equity securities or convertible debt securities | - | - |
| 3.5 | Proceeds from borrowings | - | - |
| 3.6 | Repayment of borrowings | - | - |
| 3.7 | Transaction costs related to loans and borrowings | - | - |
| 3.8 | Dividends paid | - | - |
| 3.9 | Other (provide details if material) | - | - |
| 3.10 | Net cash from / (used in) financing activities | - | - |
| 4. | Net increase / (decrease) in cash and cash equivalents for the period | ||
| 4.1 | Cash and cash equivalents at beginning of period | 79,429 | 77,345 |
| 4.2 | Net cash from / (used in) operating activities (item 1.9 above) | (710) | (3,438) |
| 4.3 | Net cash from / (used in) investing activities (item 2.6 above) | - | - |
| 4.4 | Net cash from / (used in) financing activities (item 3.10 above) | - | - |
| 4.5 | Effect of movement in exchange rates on cash held | (761) | 4,051 |
| 4.6 | Cash and cash equivalents at end of period | 77,958 | 77,958 |
| 5. | Reconciliation of cash and cash equivalents at the end of the quarter (as shown in the consolidated statement of cash flows) to the related items in the accounts | Current quarter $A'000 | Previous quarter $A'000 |
| 5.1 | Bank balances | 77,908 | 79,379 |
| 5.2 | Call deposits | 50 | 50 |
| 5.3 | Bank overdrafts | - | - |
| 5.4 | Other (provide details) | - | - |
| 5.5 | Cash and cash equivalents at end of quarter (should equal item 4.6 above) | 77,958 | 79,429 |
| 6. | Payments to related parties of the entity and their associates | Current quarter $A'000 | |
| 6.1 | Aggregate amount of payments to related parties and their associates included in item 1 | (94) | |
| 6.2 | Aggregate amount of payments to related parties and their associates included in item 2 | - | |
| 7. | Financing facilities Note: the term "facility' includes all forms of financing arrangements available to the entity. Add notes as necessary for an understanding of the sources of finance available to the entity. | Total facility amount at quarter end $A'000 | Amount drawn at quarter end $A'000 |
| 7.1 | Loan facilities | - | - |
| 7.2 | Credit standby arrangements | - | - |
| 7.3 | Other (please specify) | - | - |
| 7.4 | Total financing facilities | - | - |
| 7.5 | Unused financing facilities available at quarter end | - | |
| Not applicable | |||
| 8. | Estimated cash available for future operating activities | $A'000 | |
| 8.1 | Net cash from / (used in) operating activities (item 1.9) | (710) | |
| 8.2 | (Payments for exploration & evaluation classified as investing activities) (item 2.1(d)) | - | |
| 8.3 | Total relevant outgoings (item 8.1 + item 8.2) | (710) | |
| 8.4 | Cash and cash equivalents at quarter end (item 4.6) | 77,958 | |
| 8.5 | Unused finance facilities available at quarter end (item 7.5) | - | |
| 8.6 | Total available funding (item 8.4 + item 8.5) | 77,958 | |
| 8.7 | Estimated quarters of funding available (item 8.6 divided by item 8.3) | >10 | |
| 8.8 | If item 8.7 is less than 2 quarters, please provide answers to the following questions: | ||
Answer: Not applicable
Answer: Not applicable
Answer: Not applicable
Compliance statement
2 This statement gives a true and fair view of the matters disclosed.
Date: 30 April 2025
Authorised by: Company Secretary
(Name of body or officer authorising release - see note 4)