Beacon Energy (AIM:BCE), the full-cycle oil and gas company with a portfolio of onshore German assets through its wholly-owned subsidiary, Rhein Petroleum GmbH ("Rhein Petroleum"), announces that mobilisation of the drilling rig for the SCHB2 side track, which had originally been scheduled for mid-April, has been delayed by approximately two weeks.

The rig is currently contracted to a third-party operator for well operations located approximately 50km from the Erfelden site.

The Company has received notification from the rig contractor that due to extended ongoing operations encountered by the current operator, release of the rig is now expected at the end of April 2024.

The Company will provide a further update once mobilisation of the rig has commenced. Side track operations are expected to commence around seven days after mobilisation. The side track operation itself is expected to take approximately 14 days.

Larry Bottomley, CEO of the Company, said:

"Beacon Energy is obviously unable to control third-party delays of this kind however it is minor slippage to our previously guided timeline. We continue to prepare the site for the arrival of the rig so that the side track activities can commence as soon as possible. We look forward to the commencement of the side track as we seek to realise the full potential of the SCHB2 well and will provide further updates on mobilisation as required."

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note