Q3 2025 Production and Operations Review - Replace

In brief · summary, not quotable

Anglo Asian Mining PLC reported a record quarterly copper production of 2,287 tonnes in Q3 2025, a substantial increase from 654 tonnes in Q2 2025. Gold production reached 6,798 ounces and silver production totaled 41,605 ounces. For the nine months to September 30, 2025, copper production was 3,475 tonnes, gold production was 18,912 ounces, and silver production was 103,959 ounces. Total gold bullion sales for the nine months were 14,962 ounces at an average of $3,200 per ounce. The company's net debt increased to $14.2 million as of September 30, 2025. Revised full year 2025 guidance projects copper production of 8,100 to 9,000 tonnes and gold production of 25,000 to 28,000 ounces. Inventory was valued at $11.5 million.

Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your AAZ notes

The following amendment had been made to the Q3 2025 Production and Operations Review announcement released on 16 October at 07.00 BST under RNS number 5497D.

The amended and updated announcement, detailed below, states that gold production guidance for 2025 will be 25,000 to 28,000 ounces. All other details remain unchanged.

Anglo Asian Mining plc

Q3 2025 Production and Operations Review

Two new mines entered production during 2025

Record quarterly copper production in Q3 2025 of 2,287 tonnes

Anglo Asian Mining plc ("Anglo Asian", the Group or the "Company"), the AIM listed gold, copper and silver producer focused in Azerbaijan, is pleased to provide the following production, sales and operational review for the three months to 30 September 2025 ("Q3 2025"or the "Quarter") and nine months to 30 September 2025 ("9M 2025").

Due to the increasing proportion of copper in the Group's production in accordance with its growth strategy, the Group will no longer report total production in gold equivalent ounces. Production of copper and gold will continue to be separately reported.

Record quarterly copper production in Q3 2025

  • Copper production in Q3 2025 increased by approximately 250 per cent. compared to Q2 2025 due to the first production from Demirli and a full quarter of production from Gilar

o Copper production of 2,287 tonnes (Q2 2025: 654 tonnes)

§ 1,576 tonnes from Gedabek (Q2 2025: 654 tonnes)

§ 711 tonnes from Demirli (Q2 2025: nil)

  • Gold and silver Q3 2025 production also benefitted substantially by production from the Gilar mine

o Gold production of 6,798 ounces (Q3 2024: 2,956 ounces)

o Silver production of 41,605 ounces (Q3 2024: 3,315 ounces)

  • Substantial increase in production in Q3 2025 enhances 9M 2025 production

o Copper production of 3,475 tonnes (9M 2024: 111 tonnes)

o Gold production of 18,912 ounces (9M 2024: 7,660 ounces)

o Silver production of 103,959 ounces (9M 2024: 16,061 ounces)

Key developments in Q3 2025 across the Company's portfolio

  • First full quarter of continuous production from the Gilar mine

o 239,120 tonnes of ore grading 2.34 per cent. copper and 1.65 grammes per tonne of gold produced, including:

o 71,188 tonnes of ore grading 3.8 per cent. copper and 2.0 grammes per tonne of gold stockpiled at end of September for future processing

  • Demirli commenced production in Q3 2025, significantly enhancing the Company's copper output as part of the strategic shift towards copper

o 4,548 dmt tonnes of copper concentrate produced containing 711 tonnes of copper

o Demirli ball mill now in operation in addition to the SAG mill

  • Upgrades of the Gedabek flotation plant underway to process higher grade ores and increase operational efficiency, with the second filter press now installed

Revised full year 2025 guidance issued

  • Revised full year guidance released 9 October 2025, reflecting the impact of bringing Demirli into production during the year. The Company expects:

o Copper production of 8,100 to 9,000 tonnes

o Gold production of 25,000 to 28,000 ounces

9M 2025 sales and cash update

  • Total gold bullion sales of 14,962 ounces at an average of $3,200 per ounce (9M 2024: 9,220 ounces at an average of $2,287 per ounce)
  • The Group continues to maintain a strong focus on cash and strict cost controls, with overall negative cash flow of only $1.2 million in the Quarter, increasing net debt to $14.2 million as at 30 September 2025 compared to $14.8 million at 31 December 2024

o Negative cash flow due to start-up capital expenditure and operating expenses at Demirli until concentrate sales can commence

  • Inventory valued at $11.5 million at 30 September 2025 (30 June 2025: $7.0 million), reflecting unsold copper concentrate at Demirli

o Gedabek: $7.2 million (30 June 2025: $7.0 million)

o Demirli: $4.3 million (30 June 2025: nil)

Anglo Asian CEO Reza Vaziri commented:

"I am delighted to report our strong performance in the nine months to end September in this transformational year. The new Gilar and Demirli mines are both performing well, with very strong grades at Gilar in particular. Reflecting these two new assets being in production, we were delighted to deliver a record quarterly copper production of 2,287 tonnes, a milestone for Anglo Asian as we transition to a production profile of mostly copper."

Investor presentation

Alongside this announcement, the Company will provide a live presentation via Investor Meet Company on 16 October 2025 at 11:00am BST. Stephen Westhead, Vice President, and Bill Morgan, CFO, will host the presentation which is free to register for and can be accessed here:

Note that all references to "$" are to United States dollars.

Q3 2025 production overview

Copper production of 2,287 tonnes (Q3 2024: 11 tonnes):

o 1,576 tonnes from flotation and SART at Gedabek

o 711 tonnes from flotation at Demirli

Gold production of 6,798 ounces (Q3 2024: 2,955 ounces):

o 5,814 ounces contained within gold doré

o 984 ounces from flotation and SART production

  • Silver production totalled 41,605 ounces (Q3 2024: 3,315 ounces):

o 4,654 ounces contained within gold doré

o 36,951 ounces from flotation and SART processing

Q3 2025 sales overview

  • Total gold bullion sales of 5,181 ounces at an average of $3,430 per ounce (Q3 2024: 3,220 ounces at an average of $2,497 per ounce)
  • Total concentrate sales at Gedabek of 5,979 dry metric tonnes ("dmt") with a value of $15.5 million (Q3 2024: nil dmt, $nil)

o No sales were made by Demirli in the Quarter but inventory contained 4,547 dmt tonnes of concentrate containing 711 tonnes of copper awaiting sale

Q3 2025 financial overview

  • Cash of $10.4 million ($11.1 million at 30 June 2025) including restricted cash
  • Debt (including advance from Trafigura) of $24.6 million ($24.1 million at 30 June 2025)
  • Net debt of $14.2 million ($13.0 million at 30 June 2025)
  • Unsold gold doré and copper concentrate inventory of $11.5 million at 30 September 2025

Ore mined during 9 months to 30 September 2025

Gedabek

12 months to 31 December 20246 months to 30 June 20253 Months to 30 Sept 2025
MineOre minedAverage gold gradeOre minedAverage gold gradeOre minedAverage gold grade
(tonnes)(g/t)(tonnes)(g/t)(tonnes)(g/t)
Open pit443,6110.73529,0340.2382,9930.44
Gadir - u/g167,1211.5812,3252.21--
Gilar - u/g--106,5101.23239,1201.65
Total610,7320.96647,8690.43322,1131.34
Demirli
12 months to 31 December 20246 months to 30 June 20253 Months to 30 Sept 2025
(tonnes)(%)(tonnes)(%)(tonnes)(%)
Open pit----423,6310.43
Gedabek processing and production in 9M 2025
Ore processed by leaching
Quarter endedOre processedGold grade of ore processed
31 March 2024120,528--0.68--
30 June 2024110,2259,698-0.590.52-
30 September 2024110,152-18,0090.65-1.93
31 December 202479,835-128,3870.53-1.54
FY 2024420,7409,698146,3960.610.521.58
31 March 2025106,429-149,7630.40-1.16
30 June 2025133,153-154,9480.40-1.13
H1 2025239,582-304,7110.40-1.14
30 Sept 202547,202-156,7730.4-1.52

* includes previously heap leached ore.

Ore processed by flotation

Quarter endedOre processedGold contentSilver contentCopper content
(tonnes)(ounces)(ounces)(tonnes)
31 March 2024----
30 June 2024----
30 September 2024----
31 December 202473,9902853,985363
FY 202473,9902853,985363
31 March 2025155,4065359,516729
30 June 2025166,1351,19330,537900
H1 2025321,5411,72840,0531,629
30 Sept 2025156,7733,18585,1231,793
Gold and silver produced as gold doré
Quarter endedGold produced*Silver produced*Gold sales**Gold Sales price
(ounces)(ounces)(ounces)($/ounce)
31 March 20242,2591,5123,9252,080
30 June 20242,4331,5322,0752,350
30 September 20242,9551,9793,2202,497
31 December 20247,2806,9746,0312,655
FY 202414,92712,00715,2512,432
31 March 20255,7588,2124,7532,843
30 June 20255,6246,6995,0283,299
H1 202511,38214,9119,7813,077
30 Sept 20255,8144,6545,1813,430
Note
* including Government of Azerbaijan's share
** excluding Government of Azerbaijan's share
Gold and silver produced by leaching
Quarter endedGoldSilver
31 March 2024-2,2592,259-1,5121,512
30 June 2024-2,4332,433-1,5321,532
30 Sept 20246062,3492,9554151,5641,979
31 Dec 20245,2312,0497,2805,0061,9786,984
FY 20245,8379,09014,9275,4216,58612,007
31 March 20254,0171,7415,7585,7172,4958,212
30 June 20253,9361,6885,6244,6322,0676,699
H1 20257,9533,42911,38210,3494,56214,911
30 Sept 20254,6811,1335,8143,7359194,654
Copper concentrate production and sales
ConcentrateCopperGoldSilverConcentrateConcentrate
production*content*content*content*sales**sales**
(dmt)(tonnes)(ounces)(ounces)(dmt)($000)
Quarter ended
31 March 2024895474,89371295
30 June 2024774654,8092601,002
30 September 2024191111,336--
31 December 20241,6722661335,2131,1731,493
FY 20241,85737714616,2511,5042,790
31 March 20253,07253427122,1092,0303,616
30 June 20253,52365446225,3343,4026,299
H1 20256,5951,18873347,4435,4329,915
30 September 20256,7691,57698436,9515,97915,500
* including Government of Azerbaijan's share
** excludes Government of Azerbaijan's share
Demirli processing and production in 9M 2025
ProcessedUnitJuly to September 2025
Ore feed to plantdry metric tonnes292,950
Gradeper cent.0.45
Copper contenttonnes1,307
Production
Copper concentratetonnes4,548
Copper contenttonnes711

Q3 2025 Financial review

The Company's net debt increased from $13.0 million at 30 June 2025 to $14.2 million at 30 September 2025 as follows:

Q1 2025Q2 2025Q3 2025
$m$m$m$m$m$m
Start of quarter(14.8)(13.8)(13.0)
Revenue17.523.127.8
VAT refund0.21.81.6
Interest income0.20.20.6
Operating costs(15.2)(18.6)(22.7)
Capital expenditure(1.4)(1.5)(3.9)
Demirli expenditure-(3.8)(4.3)
Debt servicing(0.3)(0.4)(0.3)
Inflow / (outflow) in the quarter1.00.8(1.2)
End of quarter(13.8)*(13.0)*(14.2)*

*includes net advance from Trafigura of $4.9m at 30 September 2025 (30 June 2025: $4.4m; 31 March 2025: $5.0m).

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note