Anglo Asian Mining PLC ("Anglo Asian" or the "Company"), the AIM listed gold, copper and silver producer focused in Azerbaijan, announces its production guidance for the full year 2024 ("FY 2024") after receiving authorisation on 5 August to raise the wall of its tailings dam. The Company is forecasting production of between 15,000 and 19,500 gold equivalent ounces ("GEOs") comprising 250 to 850 tonnes of copper and 14,000 to 16,000 ounces of gold.

FY 2024 production guidance is as follows:

MetalFull year 2024
Production Guidance*
Gold14,000 to 16,000 ounces
Copper250 to 850 tonnes
Total**15,000 to 19,500 GEOs

* The Company does not forecast silver production as it is not material.

** The gold equivalent ounces have been computed using actual metal prices for the 7 months of January to July 2024 and a gold price of $2,500 per ounce and a copper price of $8,900 per tonne for the 5 months of August to December 2024.

The raise of the tailings dam wall commenced immediately upon receipt of authorisation. The work is progressing well, and the Company anticipates that the first raise of 2.5 metres will be completed within 3 months.

The agitation leaching plant has undergone extensive renovation and refurbishment during the last 12 months. In preparation for restarting production, the Company has undertaken cold commissioning of the plant using water for testing and has rectified all minor leaks. All crushing and grinding equipment has also been subject to extensive maintenance and is fully operational.

The Company expects the agitation leaching plant will be ready for full production and will restart in mid-September, initially processing 97,000 tonnes of stockpiled ore. The flotation plant will restart in November on an independent basis using fresh ore from the existing open pit.

The Company expects the first ore to be mined from Gilar in December, with the planned extraction and processing of approximately 35,000 to 40,000 tonnes of ore grading 1.6 grammes of gold per tonne and 2 per cent copper in the month. To treat Gilar ore, processing will be reconfigured and the agitation leaching plant will initially process Gilar ore with further processing of its tailings by flotation to produce copper.

Reza Vaziri, Chief Executive Officer of Anglo Asian Mining commented:

"We are pleased to provide guidance for this year of between 15,000 and 19,500 gold equivalent ounces as we return to full production and regular operations after receiving authorisation to raise the tailings dam wall. The tailings dam wall raise is progressing well, and we expect the first stage to be completed within the next three months.

"We have used well this period of a partial shut-down of production. In addition to extensive overhaul and refurbishment of our existing processing operations, we have completed extensive preparatory work that will enable us to deliver our strategic growth plan to become a multi-asset, mid-tier primarily copper producer. I look forward to keeping you updated on our progress in the weeks and months ahead."

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note