Operational Update: Tavsan

In brief · summary, not quotable

Tavsan Mine heap-leach pads completed, hot-commissioning underway, operational status expected late July 2025.

  • Ariana interest in Tavsan 23.5%
  • Exploration drilling completed 6,000m of up to 15,000m programme
  • Second water well depth 500m maximum
Full announcement

Select text to share a quote on X · sign in to keep highlights & notes in your AAU notes

Operational status expected from late July

Ariana Resources plc ("Ariana" or "the Company"), the AIM-listed mineral exploration and development company with gold project interests in Africa and Europe, is pleased to announce the commencement of hot-commissioning of the processing plant at the Tavsan Mine ("Tavsan" or "the Project") in Türkiye, in which Ariana has a 23.5% interest. This is an important step towards commencement of gold processing operations at Tavsan, the Company's second operating gold mine in Türkiye.

Highlights:

  • Tavsan Mine is expected to achieve operational status from late July 2025, ready for the commencement of gold production from the heap-leach.
  • Heap-leach pads are completed, with overliner aggregate currently being laid ahead of ore loading, which will follow the conclusion of statutory government inspections.
  • Hot-commissioning of the crushing and screening plants and cold-commissioning of the agglomerator is complete.
  • Approximately a year of full ore production remains stockpiled ready for loading, with crushing and screening of this material now underway.
  • Overland conveyors installed with their liners and with testing due to commence imminently.
  • Testing of the Adsorption-Desorption-Recovery ("ADR") system underway, with pumps being installed for the pregnant and barren ponds.
  • A second water well to ensure adequate water availability for the operation is being drilled to a maximum depth of 500m (currently at 200m).
  • Resource and exploration drilling programme ongoing, having completed over 6,000m of an up to 15,000m programme and testing the potential for increases in the life of mine.
  • Kerim Sener, Managing Director, commented:

"It is a pleasure to report further substantial progress over the past month at the Tavsan mine site. The Tavsan operation is nearing final commissioning ahead of ore loading onto the heap-leach pad, which is expected from later this month. The Zenit team is working around the clock to ensure that all remaining system tests are completed on the plant and heap-leach areas ahead of statutory government inspections, before the operation proceeds to production. Meanwhile, high-grade ore continues to be prioritised for processing through the CIL plant at Kiziltepe, while we prepare for the processing of the stockpile of heap-leachable ore on site, ready for loading onto the pads.

"We are very much looking forward to achieving the first gold pour from the Tavsan mine, enabling the first in-situ gold production from our second mine in Türkiye. The amount of work completed in recent months and the level of professionalism of the Zenit team and its contractors are nothing short of extraordinary. We congratulate the team on their collective efforts and wish them a successful start to heap-leach operations at Tavsan."

Figure 1: General site view at Tavsan showing the mine offices in the foreground with crushers, screens and agglomerator shown towards the top right. The overland conveyors to the Phase 1 heap-leach pad are installed and run diagonally across the image. Photograph taken in late-June 2025.

Figure 2: General site view at Tavsan encompassing the latest status of the Phase 1 heap-leach area, with the ADR plant and pregnant and barren ponds in the foreground. Overliner aggregate is being spread over the Phase 1 heap-leach pad. Photograph taken in early-July 2025.

Cleaned text: letterheads, contacts and legal notices removed. View the original announcement ↗ · Company filings. Not investment advice.

Share this quote

Quote card
Post on X WhatsApp Download image

The link opens this announcement with the quote highlighted. Quotes are checked against the original text.

Add a note