Response to Submissions Report
First Tin PLC has achieved a significant milestone with the lodgement of its Response to Submissions report for the Taronga Tin Project, moving closer to development approval. The company's wholly owned subsidiary, Taronga Mines Pty Ltd, submitted the report to the Department of Planning, Housing and Infrastructure, addressing feedback on environmental impact and project design. Crucially, only four objections were received during the public exhibition period, allowing the project to bypass a review by the Independent Planning Commission and maintain a streamlined approval pathway, reducing anticipated timelines and costs.
Select text to share a quote on X · sign in to keep highlights & notes in your 1SN notes
Taronga Tin Project Advances Towards Development Approval Following Lodgement of Response to Submissions Report
First Tin PLC, a tin development company focused on advancing low-capex projects in Australia and Germany, is pleased to announce that its wholly owned subsidiary, Taronga Mines Pty Ltd ("TMPL"), has formally lodged its Response to Submissions ("RTS") report for the Taronga Tin Project in New South Wales, Australia.
The RTS provides thorough clarifications to Submissions received from key NSW Government departments and agencies following the public exhibition phase of the Environmental Impact Statement ("EIS"). It also incorporates feedback relating to biodiversity, air quality, groundwater management, and cultural heritage to further optimise the Taronga project design. The lodgement of the RTS report represents a further key milestone in the permitting process and moves the Company closer towards securing Development Approval for its flagship Taronga Tin Project.
Importantly, as previously announced, only four objections were received during the public exhibition period for the EIS. Consequently, the project continues through the standard NSW Government departmental assessment pathway and will not be referred to the Independent Planning Commission ("IPC"), materially reducing anticipated approval timelines, execution risk and permitting costs.
Key Highlights
- Major permitting milestone achieved with formal lodgement of the Taronga Tin Project's RTS report to the Department of Planning, Housing and Infrastructure ("DPHI"), the regulatory authority.
- Streamlined approval pathway maintained following the receipt of only four objections during the EIS public exhibition period, removing the requirement for an IPC review.
- The RTS provides detailed clarifications to submissions from key NSW Government departments and agencies, including the Environment Protection Authority ("EPA"), Department of Climate Change, Energy, the Environment and Water ("DCCEEW"), Heritage NSW and the Department of Primary Industries and Regional Development ("DPIRD"), and incorporates submission feedback to optimise the Taronga project design.
Next Steps
The remaining approvals process is expected to involve:
- Final NSW Government departments and agency consultation on the RTS, coordinated by DPHI;
- Completion of the departmental assessment and preparation of draft approval conditions, to then be reviewed by TMPL ahead of formal Development Approval determination.
First Tin CEO, Bill Scotting, commented:
"The lodgement of the RTS report represents another major milestone for the Taronga Tin Project and further de-risks the pathway to development.
"The very low number of objections received during the EIS process highlights the strong foundations of the project and the extensive engagement undertaken by our team and consultants.
"We now look forward to progressing through the final stages of the approvals process and securing formal Development Approval in due course."